What is WIP Work In Progress ?

  • Examera prepare yourself for success
  • 0 comments

WIP, or Work In Progress, refers to the amount of work currently being processed at a given moment within a project or workflow. It is a core concept in Kanban, but also a key indicator of flow, efficiency, and performance in both Agile and predictive project environments.

Limiting WIP helps avoid work overload, reduce delivery delays, and improve deliverable quality. For PMI certifications such as CAPM® and PMP®, understanding WIP is essential to mastering the principles of flow management, performance optimization, and value delivery.

WIP in the Kanban System:

Kanban, originally developed within the Toyota Production System, focuses on visualizing work and managing flow through a board (physical or digital) divided into process stages such as:

  • To Do

  • In Progress

  • Done

Each task or user story is represented by a card that moves across the board as the work progresses.

The Role of WIP in Kanban:

The WIP limit sets a maximum number of items allowed in any given column or process stage.

Main goal: prevent task overload and maintain a steady flow of work.

Example:
If an Agile team sets a WIP limit of 3 items in the “In Progress” column, no new work can begin until one of the existing items is completed.

Key benefits include:

  • Reduced multitasking and fewer interruptions.

  • Increased focus and productivity.

  • Smoother workflow and faster delivery.

  • Early detection of bottlenecks.

  • Improved predictability and lead time.

WIP in Agile Environments:

In Agile frameworks such as Scrum and Kanban, managing WIP is a critical tool for continuous improvement.

  • In Scrum, WIP is limited implicitly through the team’s capacity and the fixed timebox of the sprint — only the selected backlog items can be worked on during the sprint.

  • In Agile Kanban, WIP limits are explicit, allowing teams to continuously optimize the flow and reduce inefficiencies.

WIP thus serves as a self-regulation mechanism, helping teams maintain a sustainable pace and balance workload, focus, and performance.

WIP in Predictive Project Management:

Even in predictive (Waterfall) environments, WIP tracking plays a significant role.

PMP®-certified project managers use WIP to:

  • Monitor task progress within the project management plan.

  • Identify delays, overlaps, or resource overloads.

  • Improve resource allocation and schedule control.

  • Evaluate performance using tools such as Earned Value Management (EVM).

Thus, even in predictive models, WIP contributes to maintaining control over time, cost, and quality (the classic triple constraint) — all essential competencies for PMP® and CAPM® candidates.

WIP and PMI Certifications (CAPM® & PMP®):

Understanding and managing WIP aligns with several PMBOK® Guide knowledge areas, including:

  • Schedule Management

  • Resource Management

  • Quality Management

  • Risk Management

For the CAPM® Certification:

Candidates must demonstrate their ability to identify, plan, and control workflow while optimizing resources. Managing WIP illustrates the ability to maintain balance between demand and capacity.

For the PMP® Certification:

Project managers must show proficiency in applying Lean and Agile principles to enhance performance. WIP control is part of adaptive project management, consistent with the PMBOK® Guide – 7th Edition, which emphasizes value delivery, flow, and performance.

Best Practices for Managing WIP Effectively:

  1. Set clear WIP limits for each workflow stage.

  2. Visualize work through a Kanban board (physical or digital).

  3. Identify and resolve bottlenecks as soon as WIP limits are reached.

  4. Engage the entire team in defining and respecting WIP limits.

  5. Adjust WIP thresholds regularly based on actual capacity and team feedback.

  6. Balance workload and value — start less, finish more.

WIP (Work In Progress) is far more than a tracking metric. It is a strategic management tool at the heart of Lean and Agile philosophy, applicable to both predictive and adaptive project contexts.

For CAPM® and PMP® candidates, understanding and controlling WIP means mastering how to manage projects that deliver value efficiently while respecting the time–cost–quality balance.

In essence, limiting WIP means maximizing value — less work in progress, more work completed, and better overall project performance.

Frequent PMP® & CAPM® exam questions :

These practice questions are expertly designed by Examera specialists to deepen your understanding of key concepts and enhance your skills in tackling exam-style challenges. To unlock the full experience and gain access to unlimited real exam MCQs, log in to the Examera simulators and start practicing today!

What does WIP stand for in project management?
a) Work in Planning
b) Work in Process
c) Work in Progress
d) Work in Performance
Correct answer c): WIP stands for Work in Progress, representing tasks or deliverables that have been started but are not yet completed within a project or workflow.

What is the main purpose of controlling WIP in Agile or Lean projects?
a) To reduce communication needs
b) To limit multitasking and improve flow efficiency
c) To increase resource utilization
d) To track completed deliverables only
Correct answer b): Controlling WIP prevents teams from overloading, reduces context switching, and improves focus, leading to faster delivery and higher quality outcomes.

Which Agile framework uses WIP limits as a core principle?
a) Scrum
b) Kanban
c) XP (Extreme Programming)
d) SAFe
Correct answer b): Kanban uses explicit WIP limits to manage workflow and ensure that new work isn’t started until existing tasks are completed, optimizing flow and productivity.

What happens when WIP limits are exceeded in a Kanban system?
a) Work automatically speeds up
b) Team productivity increases
c) Bottlenecks occur and flow efficiency decreases
d) The project scope expands
Correct answer c): Exceeding WIP limits leads to bottlenecks, delays, and reduced efficiency because the team’s focus is spread too thin across multiple tasks.

How can WIP limits improve project quality?
a) By increasing task switching
b) By encouraging faster completion
c) By allowing more focus and better attention to detail
d) By reducing team size
Correct answer c): Limiting WIP helps team members concentrate on fewer tasks at once, improving attention to quality and reducing defects or rework.

What tool is commonly used to visualize and manage WIP?
a) Gantt chart
b) Kanban board
c) Risk register
d) Work breakdown structure
Correct answer b): A Kanban board visually represents workflow stages and WIP limits, allowing teams to monitor progress and identify bottlenecks in real time.

In a project environment, excessive WIP typically results in:
a) Faster delivery times
b) Improved focus
c) Increased lead time and reduced efficiency
d) Lower resource utilization
Correct answer c): Too much WIP causes delays, context switching, and inefficiency, increasing overall lead time and making it harder to deliver results on schedule.

Which metric is most directly impacted by WIP levels?
a) Velocity
b) Lead time
c) Budget variance
d) Resource utilization
Correct answer b): Lead time, the total time from task start to completion, is directly affected by WIP; as WIP increases, lead time typically lengthens.

What should a team do when WIP limits are consistently reached?
a) Add more tasks to the workflow
b) Reassess process flow and resolve bottlenecks
c) Ignore the limit to maintain progress
d) Increase team size immediately
Correct answer b): When WIP limits are constantly reached, it signals process inefficiencies; teams should analyze and address bottlenecks to improve throughput.

Which of the following best describes an optimal WIP level?
a) As high as possible to maximize work started
b) Minimal, allowing steady and continuous delivery
c) Zero, ensuring no ongoing work
d) Equal to the number of team members
Correct answer b): An optimal WIP level balances workload and flow, ensuring that tasks move smoothly through the system and deliver value continuously without overloading the team.

Earn 35 PDUs for Free with our Evaluators, boost your skills and stay Certified at No Cost...

0 comments

Sign upor login to leave a comment

Get a Free decrypted 300 MCQs eBook

All the best experts together, just for You...

Examera.org is first and foremost a team of graduates from the best schools and universities in the world working together to provide you all the key elements that unsuccessful candidates have missed!