What is the Concept of a Story Point ?

  • Examera prepare yourself for success
  • 0 comments

In Agile Scrum project management, a Story Point is a relative unit of measure used to estimate the complexity, effort, and risk of a user story (or feature) in the Product Backlog.

Unlike hours or days, story points provide an abstract and comparative estimation, allowing teams to evaluate work by considering three main dimensions:

  • Technical complexity

  • Amount of work required

  • Uncertainty and risks involved

Story points are usually estimated collectively by the Scrum Team, often during Sprint Planning sessions. Estimation techniques such as Planning Poker are commonly used, where the team bases its decisions on shared references from previously completed work. To capture the increasing uncertainty as complexity grows, the Fibonacci sequence (1, 2, 3, 5, 8, 13, etc.) is often applied.

Why Are Story Points Fundamental in Scrum?

1. Measuring Velocity : Velocity represents the total number of story points completed by a Scrum Team in a sprint. It helps forecast the team’s capacity for future sprints, making it a key metric for release planning and delivery forecasting.

2. Encouraging Collective Estimation : By using story points, the whole team participates in the estimation process. This fosters shared understanding, alignment, and collaboration among developers, product owners, and other stakeholders.

3. Decoupling from Time Pressure : Story points separate estimation from hours or days, helping teams avoid unrealistic expectations from management or clients. This encourages a focus on delivering value rather than tracking time spent.

4. Adapted to Agile Context : In empirical frameworks like Scrum, where work is organized in short cycles (sprints), story points provide a flexible and adaptable basis for estimation. They support continuous inspection and adaptation during Scrum events, especially the Daily Scrum, where the team adjusts its plan daily to achieve the sprint goal.

Why Are Story Points Crucial for Agile Certifications?

Knowledge of story points is essential for Agile certifications such as PSM® (Professional Scrum Master), PSPO® (Professional Scrum Product Owner), and PMI-ACP® (Agile Certified Practitioner). These certifications frequently include questions on relative estimation, velocity, and Agile planning best practices.

Mastering story points allows candidates to:

  • Understand forecasting mechanisms in Scrum

  • Correctly answer exam scenarios involving estimation and delivery planning

  • Demonstrate professional-level understanding of value-driven project management

The concept of Story Points is a cornerstone of Agile Scrum practices. By shifting estimation from time-based to value-based, they promote team collaboration, transparency, and adaptability. For Agile practitioners, mastering story points is not only vital for day-to-day project success but also for achieving globally recognized Agile certifications that validate expertise in modern project management.

Frequent PMP® & CAPM® exam questions :

These practice questions are expertly designed by Examera specialists to deepen your understanding of key concepts and enhance your skills in tackling exam-style challenges. To unlock the full experience and gain access to unlimited real exam MCQs, log in to the Examera simulators and start practicing today!

What do story points primarily measure in Agile?
a) Time in hours
b) Business value
c) Relative effort and complexity
d) Cost of development
Correct answer c): Story points measure the relative effort, complexity, and uncertainty of completing a user story, not exact time or cost.

Which estimation technique is most commonly used with story points?
a) Delphi Method
b) Planning Poker
c) Critical Path Method
d) Earned Value Analysis
Correct answer b): Planning Poker is widely used in Agile teams to assign story points through consensus-based estimation using numbered cards.

Why are story points preferred over time-based estimation in Agile?
a) They are more accurate in predicting delivery dates
b) They eliminate the need for team discussions
c) They abstract complexity and reduce bias in estimation
d) They ensure faster task completion
Correct answer c): Story points focus on complexity and effort, reducing individual bias and time-pressure associated with hour-based estimates.

What is typically used as a baseline for story point estimation?
a) The smallest user story
b) A task duration of one day
c) The project deadline
d) The product backlog size
Correct answer a): Teams often use the smallest, simplest user story as a baseline reference to estimate other stories relative to it.

How do story points help in sprint planning?
a) By assigning tasks to individuals
b) By setting deadlines for each story
c) By determining team velocity and forecasting capacity
d) By calculating project costs
Correct answer c): Story points help teams measure velocity, allowing them to forecast how many stories can be completed in future sprints.

Which of the following is true about story points?
a) They are the same as work hours
b) They vary from team to team
c) They are fixed across all projects
d) They directly indicate business value
Correct answer b): Story points are relative and depend on a team’s agreement; one team’s estimate may differ significantly from another’s.

What is team velocity in Agile?
a) The number of tasks completed daily
b) The number of hours worked by each member
c) The number of story points completed per sprint
d) The number of backlog items created
Correct answer c): Velocity represents the number of story points a team completes in a sprint, helping forecast future delivery.

Which factor is NOT considered when assigning story points?
a) Complexity
b) Effort
c) Risk
d) Exact duration in hours
Correct answer d): Story points do not measure time; they capture relative effort, risk, and complexity rather than precise duration.

What scale is often used in story point estimation?
a) 1–10 scale
b) Fibonacci sequence
c) Percentage scale
d) Binary scale
Correct answer b): Agile teams often use the Fibonacci sequence (1, 2, 3, 5, 8, etc.) to reflect growing uncertainty with larger user stories.

What happens if a team consistently overestimates story points?
a) Velocity appears higher than actual capacity
b) Sprint planning becomes more accurate
c) The project finishes earlier
d) Backlog refinement is no longer needed
Correct answer a): Overestimation inflates velocity, making forecasts unrealistic and reducing planning accuracy, which can mislead stakeholders.

Earn 35 PDUs for Free with our Evaluators, boost your skills and stay Certified at No Cost...

0 comments

Sign upor login to leave a comment

Get a Free decrypted 300 MCQs eBook

All the best experts together, just for You...

Examera.org is first and foremost a team of graduates from the best schools and universities in the world working together to provide you all the key elements that unsuccessful candidates have missed!