What is the Planning Poker Method ?
- Examera prepare yourself for success
- 0 comments
In Agile project management and Scrum, the Planning Poker method is a collaborative estimation technique used to assess the relative effort or complexity of items in the Product Backlog. Based on collective intelligence and consensus within the development team, Planning Poker helps improve the accuracy of estimates in an Agile environment.
What is Planning Poker in Scrum?
Planning Poker is an Agile estimation technique where each Scrum Team member assigns a value to a User Story (or task) using a deck of cards, often based on the Fibonacci sequence (1, 2, 3, 5, 8, 13, etc.). These numbers represent an estimate of the relative effort, complexity, or risk.
After a brief discussion of the User Story, every team member reveals their card simultaneously. If there are significant differences between estimates, the team discusses the reasoning behind them. Arguments are shared, misunderstandings are clarified, and the team reaches a consensus-based estimate.
Why is Planning Poker Crucial in Scrum?
Encourages Discussion and Shared Understanding
Each member is encouraged to consider business needs, technical risks, and dependencies. This shared perspective aligns the team around common goals.Reduces Influence Bias
Since cards are revealed at the same time, Planning Poker prevents the most experienced or vocal team members from imposing their views on others.Fosters Team Engagement
Every team member actively contributes to the estimation process, increasing ownership of tasks and collective accountability.Improves Predictability
Regular collaborative estimation allows for better Sprint planning, more reliable forecasting, and improved backlog management.
Why Planning Poker Matters for Agile and Scrum Certifications?
Mastering Planning Poker is essential for passing Agile and Scrum certifications such as:
PSM® (Professional Scrum Master)
PSPO® (Professional Scrum Product Owner)
PMI-ACP® (Agile Certified Practitioner)
Exam questions often assess a candidate’s ability to:
Apply relative estimation principles.
Facilitate collaboration within a Scrum Team.
Prioritize the Product Backlog effectively.
Ensure transparency and realistic Sprint planning.
A deep understanding of Planning Poker highlights how estimation contributes to delivering valuable increments at the end of each Sprint, and how it integrates with Scrum events such as Sprint Planning and, indirectly, the Daily Scrum.
Estimation and the Daily Scrum: An Indirect but Strategic Link
Although Planning Poker is mainly used during Sprint Planning, its outcomes influence the Daily Scrum. Estimated tasks provide a baseline for the team to track progress, adjust workloads, and detect deviations from initial forecasts. Estimation, therefore, supports transparency, inspection, and adaptation—the three pillars of Scrum.
The Planning Poker method is a cornerstone practice in Agile and Scrum. It enhances collaboration, improves estimation accuracy, and supports continuous improvement. Mastery of this technique is not only vital for achieving Scrum certifications but also for ensuring effective planning, greater visibility of team efforts, and consistent delivery of business value in every Sprint.
Frequent PMP® & CAPM® exam questions :
These practice questions are expertly designed by Examera specialists to deepen your understanding of key concepts and enhance your skills in tackling exam-style challenges. To unlock the full experience and gain access to unlimited real exam MCQs, log in to the Examera simulators and start practicing today!
What is the main purpose of Agile Planning Poker?
a) To create the project charter
b) To estimate user story effort collaboratively
c) To assign tasks to team members
d) To prioritize backlog items
Correct answer b): Planning Poker is used to collaboratively estimate the effort or size of user stories, encouraging team consensus and reducing bias.
Which type of scale is most commonly used in Agile Planning Poker?
a) Likert scale
b) Fibonacci sequence
c) Linear scale (1–10)
d) Binary scale (0–1)
Correct answer b): The Fibonacci sequence (1, 2, 3, 5, 8, etc.) is commonly used to reflect the uncertainty in larger estimates and support relative sizing.
Who participates in Agile Planning Poker sessions?
a) Only the Scrum Master
b) Only the Product Owner
c) The entire development team
d) External stakeholders
Correct answer c): The development team participates in Planning Poker since they are responsible for estimating the work needed to complete user stories.
Why are cards revealed simultaneously in Agile Planning Poker?
a) To save time during the meeting
b) To prevent anchoring or influence by others
c) To show respect to the Product Owner
d) To rank stories in order of priority
Correct answer b): Revealing cards at the same time prevents anchoring bias, ensuring independent judgments before team discussion.
What happens when estimates in Planning Poker vary widely?
a) The Product Owner decides
b) The Scrum Master decides
c) Team members discuss reasoning and re-vote
d) The lowest estimate is chosen
Correct answer c): When estimates differ, team members discuss their perspectives and then re-vote, leading to a more accurate and shared understanding.
Which role facilitates Agile Planning Poker sessions?
a) Project Manager
b) Scrum Master
c) Product Owner
d) Development Team Lead
Correct answer b): The Scrum Master facilitates the session, ensuring collaboration and guiding the team in reaching consensus without directly influencing estimates.
What type of estimation does Agile Planning Poker promote?
a) Absolute estimation
b) Expert judgment only
c) Relative estimation
d) Historical estimation
Correct answer c): Planning Poker promotes relative estimation by comparing user stories to each other, improving accuracy over absolute time-based estimates.
What is the main advantage of using Agile Planning Poker?
a) Faster project delivery
b) Encourages groupthink
c) Builds consensus and shared understanding
d) Eliminates the need for backlog refinement
Correct answer c): Planning Poker fosters consensus and shared understanding among the team, making estimates more reliable and collaborative.
In Agile Planning Poker, what does a very high estimate typically indicate?
a) The story is simple
b) The story requires clarification or is too complex
c) The story should be prioritized immediately
d) The story has no risks
Correct answer b): A high estimate often signals that the story is unclear, large, or complex, requiring further refinement or decomposition.
When is Agile Planning Poker typically conducted?
a) During daily stand-ups
b) During sprint planning or backlog refinement
c) At project closure
d) During sprint review
Correct answer b): Planning Poker is used in sprint planning or backlog refinement sessions to estimate user stories before they are committed for development.
Earn 35 PDUs for Free with our Evaluators, boost your skills and stay Certified at No Cost...
Get a Free decrypted 300 MCQs eBook
All the best experts together, just for You...
Examera.org is first and foremost a team of graduates from the best schools and universities in the world working together to provide you all the key elements that unsuccessful candidates have missed!